Monday, May 14, 2007

14.05.2007

What a day! When me, Sifiso and Karabo got to site, we met kasia who had arrived an hour earlier and had negotiated with Benny and Benji to lower their fee. However, it was clear that we were now going to have to work harder than ever to get the work done, because with the lower fee, all the labour was going to come from us and the volunteers! This predicament showed how strong the community spirit was because so many volunteers showed up this particular day and we even managed to remove all the top soil before lunch.
Benny later on told us, because the fee had been reduced so much, he didn’t think he could afford to supervise us the whole day, but said he would give the supervision of the project over to two other builders, Sonny Boy and Solomon, and would come and check in from time to time on how the work was going. I was disappointed to see him go, but that was short lived when I saw how efficient Sonny Boy and Solomon were. We managed to start mixing and pouring the concrete into the trenches after lunch, only stopping to buy more sand and by the time we left Kwathema at 4:30pm the foundations were 2/3 done, and Sonny Boy and Solomon reassured us that they would keep working to make sure they were finished before the end of the day.


Emergency Drawing Delivery-Tuesday May 14

Today I woke up early to make it to Kwathema by 6:30 so that Phillip the legendary welder from Highlands could give me a quote. Dont know where the bloody hell the money for it will come from but alas-lets hope we come in under R3000- thats the limit. Made it back to Jozi by 9:00 for an intense day of Discourse with Grandmaster Eduardo

Drilling Begins

We all met in the workshop at 07h30 this morning to begin drilling holes in our C-section for the balustrades.

We began the morning by talking to Peter Kesley (the workshop manager at Wits University) and briefing him on our project and our design for the beerhall. He’s a really knowledgeable man and I really get the feeling that he enjoys imparting his knowledge and experience with students who are eager and willing to learn from him.

We had a really good production line happening with Catherine marking the various hole positions on the steel. Guy was next in the production line- he drilled the 5mm pilot holes and then lastly I drilled the 12mm holes, with the help of Robyn, who held the steel in position and applied cutting paste to each of the holes that I drilled.

Drilling began in the workshop. Started at 07h30 and finished at 10h30.
Had a great production line- Catherine marked the position of the holes on the steel, Guy drilled the 5mm pilot holes, I drilled the 12mm holes with the help of Robyn who carried the steel and applied cutting paste to each of the holes I drilled.

The process of drilling was very quick and we were done by about 11h00. We then took along a sample piece of steel to site with us for the purposes of marking off the hole positions on the concrete structure.

Guy bought along a really fancy and incredibly useful piece of land surveying machinery that assisted us marking out the holes on the structure. This process went smoothly and when that was done it was time for us to start drilling the holes.

We borrowed a cordless pneumatic drill from Richard at Fischer to drill approximately 80 holes in the structure. This was a really great piece of machinery although, being battery powered, the drill could go on forever and we had to keep stopping to charge the battery.

Sunday, May 13, 2007

powwow

on friday, catherine suggested we have a meeting. so we met at her house. it was sunday. khula did not come - i dont know why. little guaga, her black and white kitten was so happy to see us! we reassessed our program and more specifically our budget. hannah had mentioned to us that she was not happy that we were exceeding our r10000 budget – she also mentioned that we should be utilizing what we could find in kwa thema rather than becoming fundraisers! and so we declined sab’s generous r15000 donation and cut our program right back. the refusal of the sponsorship was not an easy decision to make – but it was the right one.

the project has taken so many turns and the posts have shifted so many times, and keep on shifting! we decided to base our decisions on the function or non-function of the space. we ensured that none of the interventions that we were proposing would make the space determined or static or even prescribed for any particular use. we also considered our budget of course! and so the slide and the jungle gym were scrapped, along with the seating. we also agreed that we should pursue lighting more seriously with the council.

the meeting ended on a positive note – although we all felt that the beerhall was going to be less of a place without these things.

Saturday, May 12, 2007

First Day In Kwathema

Mood: excitement
Song in mind: Jennifer Lopez-feel so good
Location: Kwa-Thema
Mission: Meet Volunteers and site walk

This was the first day in Kwa-Thema and we got the opportunity to meet the volunteers for the first time and I was really looking forward to the project. Aspects that I like concerning the project are community involvement and interaction, and the fact that the project is real. Many of us have never been involved in projects of this magnitude before. I enjoyed meeting the volunteers.

We took a walk to all of the potential sites, but the one I found most intriguing was the space between the houses because I could not believe that a car could actually fit within that space. I was moved by the Chess Park site as it goes beyond architecture and begins to deal with the fulfilment of someones dreams and ambitions to create an environment where children and the community at large can come together and play. He showed us his plan for the site and my impression of the site is that it has a huge potential for growth and development. If one is to partake in this project, I feel that it must be designed as such.

We got together at the library to talk about the history of Kwathema and the type of interventions we would like to make at this stage from different points of view; councillor, resident, tourist, etc. the views that came out were inter-related and similar indicating similar thinking patterns. This discussion really helped to put my mind at ease as the levels of intervention on the different sites became clear.

I am really looking forward to the rest of the project.

Friday, May 11, 2007

politics and perusals

gareth and catherine collected our steel in strydom park at 9:20am. i arrived at the workshop a little late so had missed out on a bit but it was liberating to finally see some material! and it was so sexy! i never thought i would feel so fond of a pile of 100x50mm c-sections! we discussed our way forward and ran our ideas past peter, the workshop manager. everything seemed to be going smoothly.

we drove to fischer to meet with kerry’s brother, richard as kerry was away. we became concerned that the anchors that they have proposed for our balustrade would not be sufficient to hold up the monstrous balusters – but he assured us that they would. upon promising to always, throughout our entire professional careers, specify fischer as the number one fixing, he donated 100 anchors to our project! richard then give us a lesson on rotary drilling and generously lent us their r6000 portable drill. we were overwhelmed by his generosity – not only his actually, but the entire groups’. it seemed extraordinary that such a bunch of people still existed in this world. i can assure anyone reading this, that fischer definitely has a far superior product to others on the market – if only for this reason! we walked out feeling completely overwhelmed.

at 2pm, we began a workshop with bernd and christopher. it was lengthy and at times heated, or should i say, rather intensely discursive! they reiterated their concerns about our lack of process and analysis, and our subsequent failure in making informed design decisions. they spoke about process and networking and the clear distinction between form and modernist attitudes. we were quiet and bewildered by the news. only a week earlier, we had presented to council and had, as we thought, received the go-ahead. why were they throwing this spanner into our works? and why was hannah shifting the goal posts? we have only 2 weeks until our launch! the frustration and disheartenment was huge and the tension between us and them rose. all of our hard work and what we thought was process, seemed to be insufficient for their requirements. it became clear to me that the politics in design and designing politics that they were referring to was not about kwathema and its people or even about the project, but rather about the varying agendas of the people around the table. ifg ulm vs hannah vs us students! our hearts broke and the community’s broke with ours.

we stayed behind to propose a possible r15000 donation from sab to hannah. she suggested we take it for a possible future project. but we knew that they would not give it to us under this pretext.

we left feeling gray.

The politics of design funding

We got to site very early yesterday (Thursday) to measure the depths of all the balusters and thus determine the length at which our C-sections should be cut. The process went smoothly and we were able to get the information to Fleet Steel by 10am so that they could begin. The remarkable, wonderful sight when we arrived was of a clean beerhall, confirming Stan’s excited call to Guy on Wednesday to say that he must ‘Come now!’ Mr Cindi, Stan, Dudley, Amos, Eric and some volunteers from the ANC Youth League had spent the last few days clearing rubbish and sweeping. This was a mark of a real investment by members of the community in the project. By mid-morning, our new band of volunteers had begun to reassemble to finish off the last remaining spot on the east side. At first, it was tricky working out the dynamics of this group as they had really just appeared out of nowhere. Robyn and I went off to buy gloves and face masks because the wind was sweeping up the dust terribly. We also bought rolls and apples and chips and Coke which we shared on our return. There were a number of things happening, including appointments with subcontractors for quotes, arranging workshops with the local primary school, etc, but when Hannah and the Germans arrived, their impression was clearly that nothing was happening on site. This was an unfortunate assumption as Hannah then started telling us what to do, and how not to lose people’s energy. She also briefed us on the Germans’ reactions to our drawings pinned up in the KwaThema room back at Wits. They had apparently been distressed at the ‘fixed’ quality of the design with no evidence of the process of having come to it. Hannah’s suggestion, in the light of their comments, that we not build anything was very difficult to take on board, having just confirmed an order for R5000’s worth of steel. Then came a little Q&A with Christopher and Berndt in which their main line of inquiry seemed to be how we had arrived at our design. My answer – probably somewhat defensive – was that, yes, we had, to a very large degree, and under strict scheduling pressures, imposed the programme on the site, based on a limited amount of observation of its use and of interaction with the community. The process-based approach that they seemed to want had simply not been catered for in our very tight seven-week course in which the emphasis had been on coming very quickly to a design, and then sourcing materials, because building would take place in the last three weeks. Oh boy!
Later in the morning, Gary Theodosioeu, a consultant from the Cement and Concrete Institute, arrived on site, as we’d arranged. His examination with Guy was very thorough and his assessment was that there were some serious spots which were problematic but which in order to be fixed would need to be broken back, and sealed before being patched. He proposed that we use props in these troublesome spots and reassured us that nothing would fall down in the next ten years.
We also heard a sample of potential poetry for our launch from Loli and Molin who I’d tracked down off a poster advertising a Freedom Day poetry and picnic event. Mpumi also wants to perform which is great, and Lawrence made some encouraging noises about not having written in a while… We also had a workshop session with all the volunteers to explain the project to those who were new and to discuss the launch. Lunga said he was a DJ and could organise sound for us. We were further cheered up in the afternoon by a fantastic group effort in clearing the mounds of earth, rubble and rubbish on the south and west sides of the beerhall. Everyone seemed to be glowing with a real sense of achievement. Late in the afternoon Robyn stopped and harnessed a huge yellow roller driving down the road and rode back with the drivers to the site where they squashed down our growing pile of rubbish with great drama. The braai at Stan’s in the evening was fun though we went home feeling confused and apprehensive about the turn of events and having lost out sense of humour.
This morning, Gareth and I met at Fleet Steel to collect the C-sections. I panicked when I saw their size, deciding that we had seriously over-spec’d them, but back at varsity Robyn, Guy and Gareth thought they looked good. After offloading into the workshop, we decided to pay Fischer a visit with a member to check that the anchors we had discussed with Kerry would still be appropriate. He was still away, but we had a meeting with Richard, his brother, who was equally generous and friendly. Expecting only to get some technical advice, we left with 100 bolts and a fantastic borrowed battery-operated concrete drill in hand.
In the afternoon, we had a ‘workshop’ with the Germans. Hannah opened the meeting by suggesting that our designs were ‘premature’ and ‘precocious’ and questioning the politics at stake – why were we doing what we were doing, was one of many questions to be asked about the politics of the process. It turned out that Christopher and Berndt’s agenda is to assemble as much material as possible on the design process for exhibition and publication and thus it seemed a pity that their intentions had not been made clear to Hannah or to us from the start. They suggested we look like children at the context – I think they meant with fresh eyes but it sounded rather romantic and idealised. Their proposal was that we should define or design a ‘first step’ only but that this must be the right step in order to open up possibilities – which seemed like an impossibility: there can surely be no such thing as a single, right first step. They said there was no way they could show our PhotoShopped images in Germany: perhaps they were too cheesy and unsophisticated for that audience, and also not what was expected from gritty Africa. These images were something that Hannah has repeatedly and specifically requested – she had thought they were good tools for selling the scheme to the council. The Germans wanted a meta-analysis of every document explaining its role in the whole design process. There seemed to be a dichotomy between the design-build brief that we had got and their expectation of a focus on the relationship between politics and design which was the basis on which the grant had been given. Hannah closed things off by helpfully pointing to the tension between the reduction of choices that by definition traditional building carries out and the process of opening up the meaning of a site. Could we cap the power of architecture by using certain forms which were more accommodating? It was difficult not to see a direct reference to our project, though, in her proposal that one ‘limit the damage’ one does by building.